 LAPM Chapter 17: Project Completion

  1. The local agency person who signs the Final Inspection Form FIF-6/05 shall be the one with the authority to accept the completed contract for the agency and authorize final payment to the contractor.
  2. True

    False
(LAPM Section 17.3, under "State-Authorized Projects", and also under "FHWA Full Oversight", page 17-3)