Day 1

Module 1 (8:00 AM – 10:00 AM)

  • Selection/Authorization of Public Works Projects 
  • Design
  • Acceptance and Maintenance
    • Description of Construction Team
    • Inspector and Inspection
    • Inspection policy
    • Inspection practice
    • Goals of testing and Inspection Plan
  • Construction Documents
    • Contracts
    • Plans
    • Specifications
    • Addenda
    • Change Orders
    • Supplemental Project Information
  • Interactive Engagement Exercise

Module 2 (10:00 AM – 12:00 PM)

  • Resident Inspector (or Resident Engineer) & Project Delivery
    • Inspector’s Administrative Duties
    • Inspector Authority
    • Contract Compliance Requirements
    • Measurement & Payment
    • Project Closeout

Lunch (12:00 – 1:00 PM) 

Lunch is not provided as part of the seminar (you are on your own)

Module 3 (1:00 PM – 3:00 PM)

  • Legal Constraints for Public Works Projects
    • California Contract Code
    • NEPA & CEQA
    • Stormwater (NPDES)
    • Safety (OSHA & Cal/OSHA)
    • Hazardous Materials
    • Labor Code/Prevailing Wage 
    • Other
  • Interactive Engagement Exercise

Module 4 (3:00 PM – 5:00 PM) 

  • Construction and Inspection for the Inspector
  • Earthworks
    • Soils
    • Geotechnical aspects of grading
    • Types
    • Normal order of construction
    • Inspection

Day 2

Module 5 (8:00 AM – 10:00 AM) 

  • Pipelines & Piles and Piling
  • Pipelines – Sewer, Storm Drain, Water
    • Materials
    • Installation
    • Trench Restoration
    • Testing
    • Special Construction Methods 
  • Piles and Piling
    • Why used 
    • Types
      • End Bearing
      • Friction
      • Combination
    • Materials
    • Inspection
  • Interactive Engagement Exercise

Module 6 presentation (10:00 AM – 12:00 PM)

  • Portland Cement Concrete (PCC)
    • Materials
    • Plain versus reinforced
    • Pre-stressed versus Post-tensioned
    • Construction
      • Make concrete
      • Transport & Placement
      • Curing
      • Problems 
  • Waterstops
  • Interactive Engagement Exercise

Lunch (12:00 – 1:00 PM) 

Lunch is not provided as part of the seminar (you are on your own)

Module 7 (1:00 PM – 3:00 PM)

  • Paving and Structural Connections 
  • Pavements
    • Pavement Design
    • Pavement Construction
    • Inspection 
    • Pavement Maintenance 
  • Structural Connections
    • Bolting 
    • Welding
    • Other 
  • Interactive Engagement Exercise

Module 8 (3:00 PM – 5:00 PM)

  • Protective Coatings & Project Closeout 
  • Painting and Protective Coatings
    • Principles of Corrosion
    • Paint Prep
    • Surface Conditions
    • Painting and Coating
    • Inspection
    • Failures
    • Restricted Materials 
  • Project Closeout
    • Preparation for Closeout
    • Beneficial Occupancy/Partial Utilization
    • Liquidated Damages
    • Early Completion
    • Punch List
    • Contractor Obligations
    • Engineer Obligations
    • Completion versus Substantial Completion
    • Performance
    • Liens and Stop Notices 
  • Interactive Engagement Exercise